Urgent Maintenance at Oslo Datacenter
Scheduled Maintenance Report for Servebolt
Completed
The power infrastructure upgrade has been completed successfully.
Posted Oct 10, 2024 - 17:48 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 10, 2024 - 15:00 CEST
Scheduled
Please be advised that the facility where our services are hosted will undergo a power infrastructure upgrade to enhance capacity and reliability. This maintenance includes both hardware and software enhancements, such as the installation of new power and battery modules.

During this time, the facility will operate on generator power to ensure uninterrupted service. While no downtime is anticipated, the power system should be considered at risk until the upgrade is complete.

Specialists will be on-site to carry out this upgrade safely and efficiently.

We appreciate your understanding and patience. If you have any questions or concerns, please contact our support team.

Thank you for your continued trust in our services.
Posted Oct 09, 2024 - 15:54 CEST
This scheduled maintenance affected: Servebolt Cloud OSL.